Wilton CCGT Project 1

Wilton CCGT Project 1 is a gas project of 850 MW in NESO's TEC Register of 23 Oct 2026, connecting at Greystones B 275kV Substation (NGET). Status: Consents Approved.

Customer
SEMBCORP UTILITIES (UK) LIMITED
Connection site
Greystones B 275kV Substation
Transmission owner
NGET
Technology
Gas
Capacity (TEC)
850 MW
Agreement
Direct Connection
Status
Consents Approved
MW effective from
30 Oct 2035
NESO project number
PRO-006733