Grid GuardianOpen the evidence in the app

Whitehouse BESS station

Whitehouse BESS station is a demand, storage project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Whitehouse 275kV Substation (SHET). Status: Scoping. Gate 1.

Customer
IGP INTERNATIONAL PROSPECTING LIMITED
Connection site
Whitehouse 275kV Substation
Transmission owner
SHET
Technology
Demand, Storage
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-002237