Westerton Lane BESS
Westerton Lane BESS is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Busby 275kV (SPT). Status: Scoping.
- Customer
- Apatura Project 22 Ltd
- Connection site
- Busby 275kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 150 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 17 Sept 2029
- NESO project number
- PRO-003267
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.