West Weybridge (Tertiary)
West Weybridge (Tertiary) is a storage, solar project of 49.9–57 MW in NESO's TEC Register of 23 Oct 2026, connecting at West Weybridge 275kV Substation (NGET). Status: Scoping.
- Customer
- EL (WEST WEYBRIDGE) LIMITED
- Connection site
- West Weybridge 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 49.9–57 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Oct 2025, 31 Oct 2027
- NESO project number
- PRO-000552-1, PRO-000552-2
Also at West Weybridge 275kV Substation
| Project | Technology | MW |
|---|---|---|
| West Weybridge | Storage | 57 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.