Grid GuardianOpen the evidence in the app

Weaver Island 150MW BESS

Weaver Island 150MW BESS is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Elton (Merseyside 132kV Substation) (NGET). Status: Scoping. Gate 1.

Customer
Weaver Island BESS Ltd
Connection site
Elton (Merseyside 132kV Substation)
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
150 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-002714

Source