Grid GuardianOpen the evidence in the app

Walpole Flexible Generation

Walpole Flexible Generation is a gas, storage project of 2,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Walpole 400kV Substation (NGET). Status: Scoping.

Customer
FLEXIBLE GENERATION 1 LTD
Connection site
Walpole 400kV Substation
Transmission owner
NGET
Technology
Gas, Storage
Capacity (TEC)
2,000 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Jun 2033
NESO project number
PRO-002440

Also at Walpole 400kV Substation

ProjectTechnologyMW
Kings Lynn AGas395
Norfolk001Storage, Solar860
Peak Gen BEGAOil & AGT (Advanced Gas Turbine)20.5
PeterboroughGas245
Sutton BridgeGas850
Walpole 1 (Tertiary)Storage, Solar57
Walpole 2 (tertiary)Storage, Solar100
Walpole Grid Services FacilityReactive Compensation0