Grid GuardianOpen the evidence in the app

Walham 700MW BESS

Walham 700MW BESS is a storage project of 700 MW in NESO's TEC Register of 23 Oct 2026, connecting at Walham 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
GPC 1154 Ltd
Connection site
Walham 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
700 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
17 Nov 2033
NESO project number
PRO-002551

Also at Walham 400kV Substation

ProjectTechnologyMW
Walham PV & BESS SubStorage, Solar249

Source