Grid GuardianOpen the evidence in the app

Wakeleys BESS

Wakeleys BESS is a storage, solar project of 480 MW in NESO's TEC Register of 23 Oct 2026, connecting at Wakeleys 400kV (NGET). Status: Scoping. Gate 1.

Customer
EPL NEWCO6 LIMITED
Connection site
Wakeleys 400kV
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
480 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2033
NESO project number
PRO-003921

Source