Grid GuardianOpen the evidence in the app

UK105-B Upland Arms

UK105-B Upland Arms is a storage, solar project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Llandyfaelog 400/132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
URUK BESS LIMITED
Connection site
Llandyfaelog 400/132kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
200 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
6 Dec 2036
NESO project number
PRO-004649

Also at Llandyfaelog 400/132kV Substation

ProjectTechnologyMW
Brechfa Dau Wind FarmStorage, Onshore wind110.8
GALILEO 06Onshore wind175

Source