Torness BESS Station
Torness BESS Station is a storage project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Thorntonloch 400kV Substation (SPT). Status: Scoping. Gate 1.
- Customer
- IBV Torness Energy Park Limited
- Connection site
- Thorntonloch 400kV Substation
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 240 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2031
- NESO project number
- PRO-004904
Also at Thorntonloch 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Elmya Dunbar BESS | Storage | 400 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.