Tormsdale Windfarm is a storage, solar project of 70 MW in NESO's TEC Register of 23 Oct 2026, connecting at Mybster 3 132/33kV Substation (SHET). Status: Scoping.
- Customer
- ASUK HOLDCO 1 LIMITED
- Connection site
- Mybster 3 132/33kV Substation
- Transmission owner
- SHET
- Technology
- Storage, Solar
- Capacity (TEC)
- 70 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 30 Jun 2028
- NESO project number
- PRO-001904
Also at Mybster 3 132/33kV Substation
| Project | Technology | MW |
|---|---|---|
| Bad a Cheo Wind Farm | Onshore wind | 26.65 |
| Halsary Wind Farm | Onshore wind | 28.5 |
| Lisa's Battery Storage | Storage | 47 |
| Watten Wind Farm | Onshore wind | 52.8 |