Thurcroft Storage

Thurcroft Storage is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Leeds South Connection Node B 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
BSR APPLICATIONS LIMITED
Connection site
Leeds South Connection Node B 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2039
NESO project number
PRO-005889

Source