Thornton PV & BESS Sub
Thornton PV & BESS Sub is a storage, solar project of 249.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Thornton B 400kV Substation (NGET). Status: Scoping.
- Customer
- O&G Solar (SPV 57) Limited
- Connection site
- Thornton B 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 249.9 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 26 Oct 2035
- NESO project number
- PRO-004141
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.