Grid GuardianOpen the evidence in the app

TH Bridge Farm

TH Bridge Farm is a storage project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Imperial Park B 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
FRV Powertek Limited
Connection site
Imperial Park B 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
400 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-003425

Also at Imperial Park B 400kV Substation

ProjectTechnologyMW
IPC Grid TremorfaStorage1,000

Source