Sundon Farm

Sundon Farm is a storage, solar project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Dunstable 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
548 UK INVESTMENT HOLDINGS LIMITED
Connection site
Dunstable 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
29 Oct 2032
NESO project number
PRO-002685

Also at Dunstable 400kV Substation

ProjectTechnologyMW
Hipsey BESSStorage240
Hockliffe GEC (Ethos Green)Storage, Solar850
Sundon Farm 2Storage, Solar700
Woburn Solar FarmSolar840