Grid GuardianOpen the evidence in the app

Stracathro BESS

Stracathro BESS is a demand, storage project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Stracathro BESS 275kV Substation (SHET). Status: Scoping. Gate 1.

Customer
Opdenergy UK 8 Limited
Connection site
Stracathro BESS 275kV Substation
Transmission owner
SHET
Technology
Demand, Storage
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Jun 2032
NESO project number
PRO-002392