Stracathro BESS is a demand, storage project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Stracathro BESS 275kV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- Opdenergy UK 8 Limited
- Connection site
- Stracathro BESS 275kV Substation
- Transmission owner
- SHET
- Technology
- Demand, Storage
- Capacity (TEC)
- 249 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Jun 2032
- NESO project number
- PRO-002392
Source