Stoke Bardolph 400 is a storage, solar project of 200–400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Stoke Bardolph 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- ENSO GREEN HOLDINGS LIMITED
- Connection site
- Stoke Bardolph 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 200–400 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2031, 31 Oct 2034
- NESO project number
- PRO-002191-1, PRO-002191-2, PRO-002191-3
Also at Stoke Bardolph 400kV Substation
| Project | Technology | MW |
|---|---|---|
| RAF Newton PV solar | Solar | 149.7 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.