Spalding PV and BESS Station is a storage, solar project of 480 MW in NESO's TEC Register of 23 Oct 2026, connecting at Weston Marsh 400kV Substation (NGET). Status: Scoping.

Customer
ETP UK 1 LTD
Connection site
Weston Marsh 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
480 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Jul 2033
NESO project number
PRO-002768