South Powrie Farm
South Powrie Farm is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Tealing 132kV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- QAIR RENEWABLES UK LIMITED
- Connection site
- Tealing 132kV Substation
- Transmission owner
- SHET
- Technology
- Storage
- Capacity (TEC)
- 500 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2033
- NESO project number
- PRO-004353
Also at Tealing 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Akku Tealing Battery Storage | Storage | 500 |
| Myreton BESS | Storage | 200 |
| Seagreen 1 Offshore Wind Farm | Offshore wind | 1,075 |
| Tealing Energy Park | Storage | 1,400 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.