Grid GuardianOpen the evidence in the app

Smeaton BESS

Smeaton BESS is a storage project of 228 MW in NESO's TEC Register of 23 Oct 2026, connecting at Smeaton 400kV (SPT). Status: Consents Approved. Gate 2.

Customer
KONA ASSET 3 LIMITED
Connection site
Smeaton 400kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
228 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
31 Jul 2028
NESO project number
PRO-002635

Also at Smeaton 400kV

ProjectTechnologyMW
Crossgatehall BESSStorage300

Source