Sevington is a gas project of 10 MW in NESO's TEC Register of 23 Oct 2026, connecting at Sellindge 132kV Substation (NGET). Status: Built.
- Customer
- UK POWER RESERVE LIMITED
- Connection site
- Sellindge 132kV Substation
- Transmission owner
- NGET
- Technology
- Gas
- Capacity (TEC)
- 10 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-000264
Also at Sellindge 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Partridge Farm BESS | Storage | 500 |
| Sellindge (Tertiary) | Storage | 49.9–76 |
| Sellindge Grid Stability Services | Reactive Compensation | 0 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.