Sealtainn Offshore Wind Farm

Sealtainn Offshore Wind Farm is a offshore wind project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Northern Shetland 400kV Substation (SHET). Status: Scoping.

Customer
Shetland Offshore Wind Limited
Connection site
Northern Shetland 400kV Substation
Transmission owner
SHET
Technology
Offshore wind
Capacity (TEC)
500 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-002670

Also at Northern Shetland 400kV Substation

ProjectTechnologyMW
ARVEN OFFSHORE WIND FARMOffshore wind1,800
Arven South Offshore Wind FarmOffshore wind500