Seabank (Tertiary)

Seabank (Tertiary) is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at SEABANK 400/33kV SUBSTATION (NGET). Status: Awaiting Consents. Gate 1.

Customer
PIVOTED POWER LLP
Connection site
SEABANK 400/33kV SUBSTATION
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Awaiting Consents
MW effective from
1 Nov 2023
NESO project number
PRO-001068

Also at SEABANK 400/33kV SUBSTATION

ProjectTechnologyMW
SeabankGas1,234
Severn Road AvonmouthStorage, Gas135