Sand Quarry Old Glasgow Road BESS
Sand Quarry Old Glasgow Road BESS is a demand, storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Giffordland 400/132kV (SPT). Status: Scoping.
- Customer
- GPC 1134 Ltd
- Connection site
- Giffordland 400/132kV
- Transmission owner
- SPT
- Technology
- Demand, Storage
- Capacity (TEC)
- 100 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 7 May 2029
- NESO project number
- PRO-002706
Also at Giffordland 400/132kV
| Project | Technology | MW |
|---|---|---|
| GIFFORDLAND 200MW FIELD BESS | Storage | 200 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.