Saltend

Saltend is a gas project of 1,100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Saltend South 400kV Substation (NGET). Status: Built.

Customer
SALTEND COGENERATION COMPANY LIMITED
Connection site
Saltend South 400kV Substation
Transmission owner
NGET
Technology
Gas
Capacity (TEC)
1,100 MW
Agreement
Direct Connection
Status
Built
NESO project number
PRO-000059