SAGE
SAGE is a demand, solar project of 20 MW in NESO's TEC Register of 23 Oct 2026, connecting at St Fergus Mobil 132/11kV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- SAGE NORTH SEA LIMITED
- Connection site
- St Fergus Mobil 132/11kV Substation
- Transmission owner
- SHET
- Technology
- Demand, Solar
- Capacity (TEC)
- 20 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Apr 2029
- NESO project number
- PRO-002119
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.