Rochdale BESS
Rochdale BESS is a storage project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Rochdale 275kV Substation (NGET). Status: Consents Approved. Gate 2.
- Customer
- Rochdale (BES) Ltd
- Connection site
- Rochdale 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 57 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Consents Approved
- MW effective from
- 30 Oct 2029
- NESO project number
- PRO-001805
Also at Rochdale 275kV Substation
| Project | Technology | MW |
|---|---|---|
| Calderdale Wind Farm 240 MW | Onshore wind | 170 |
| Green Frog @ Goose House Lane | Gas | 21 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.