Grid GuardianOpen the evidence in the app

Ranby

Ranby is a storage, solar project of 600 MW in NESO's TEC Register of 23 Oct 2026, connecting at Jubilee Farm 275kV Substation (NGET). Status: Scoping. Gate 1.

Customer
SSE DE SOLAR HOLDCO LIMITED
Connection site
Jubilee Farm 275kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
600 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Aug 2034
NESO project number
PRO-002557

Also at Jubilee Farm 275kV Substation

ProjectTechnologyMW
Jubilee FarmStorage, Solar200
Lightsource Jubilee FarmStorage, Solar, Onshore wind240