Pollington Hybrid is a storage, solar, onshore wind project of 440 MW in NESO's TEC Register of 23 Oct 2026, connecting at Leeds North Connection Node B 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
EDF ENERGY RENEWABLES LIMITED
Connection site
Leeds North Connection Node B 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar, Onshore wind
Capacity (TEC)
440 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-005049