Penrhiwdarren Farm

Penrhiwdarren Farm is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Cilfynydd 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
QAIR RENEWABLES UK LIMITED
Connection site
Cilfynydd 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
500 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
15 Sept 2037
NESO project number
PRO-003828

Also at Cilfynydd 400kV Substation

ProjectTechnologyMW
BESS CilfynyddStorage200
CilfynyddStorage, Solar, Onshore wind400
Cilfynydd 2Storage240
Cilfynydd BESSStorage349.9
Cilfynydd Green Energy CentreDemand, Storage, Solar, Onshore wind400–1,025
Cilfynydd Grid Stability ServicesReactive Compensation0
Merthyr Solar and BatterySolar110–175
Twyn Hywel CillfynyddOnshore wind107.8