Oldbury (Tertiary)

Oldbury (Tertiary) is a storage project of 49.9–57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Oldbury 275kV Substation (NGET). Status: Awaiting Consents. Gate 1.

Customer
PIVOTED POWER LLP
Connection site
Oldbury 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9–57 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Awaiting Consents
MW effective from
30 Jun 2027, 31 Oct 2037
NESO project number
PRO-001074-1, PRO-001074-2