Ocker Hill - Gresham House
Ocker Hill - Gresham House is a storage project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ocker Hill 275kV Substation (NGET). Status: Consents Approved. Gate 2.
- Customer
- Ocker Hill Storage Limited
- Connection site
- Ocker Hill 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 240 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Consents Approved
- MW effective from
- 30 Oct 2029
- NESO project number
- PRO-002213
Also at Ocker Hill 275kV Substation
| Project | Technology | MW |
|---|---|---|
| Ocker Hill Tertiary Connection | Storage | 57 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.