Grid GuardianOpen the evidence in the app

Newtonwood BESS

Newtonwood BESS is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Chesterfield GSP (NGET). Status: Under Construction/Commissioning.

Customer
CARE POWER (NEWTONWOOD) LIMITED
Connection site
Chesterfield GSP
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Embedded
Status
Under Construction/Commissioning
MW effective from
15 Aug 2023
NESO project number
PRO-004156