Net Zero Teesside Power Project
Net Zero Teesside Power Project is a gas, demand project of 860 MW in NESO's TEC Register of 23 Oct 2026, connecting at Tod Point 275kV Substation (NGET). Status: Consents Approved.
- Customer
- NET ZERO TEESSIDE POWER LIMITED
- Connection site
- Tod Point 275kV Substation
- Transmission owner
- NGET
- Technology
- Gas, Demand
- Capacity (TEC)
- 860 MW
- Agreement
- Direct Connection
- Status
- Consents Approved
- MW effective from
- 30 Jul 2027
- NESO project number
- PRO-001400
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.