NEL Limes

NEL Limes is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at North Humber Connection Node B 132kV Substation (NGET). Status: Scoping.

Customer
SFEL Two Limited
Connection site
North Humber Connection Node B 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Embedded
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-004413