NEL Lackenby
NEL Lackenby is a storage project of 228 MW in NESO's TEC Register of 23 Oct 2026, connecting at Teeside Connection Node A 132kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- Newton Energi Limited
- Connection site
- Teeside Connection Node A 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 228 MW
- Agreement
- Embedded
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Oct 2035
- NESO project number
- PRO-003658
Also at Teeside Connection Node A 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Lackenby PV & BESS Station | Storage, Solar | 240 |
| NatPower Teesside Green Energy Park | Storage | 1,000 |
| Tees Renewable Energy Plant | Bioenergy | 285 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.