Moffat BESS is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Moffat 400kV Substation (SPT). Status: Scoping. Gate 1.

Customer
Conrad Energy (Developments) II Limited
Connection site
Moffat 400kV Substation
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
500 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2031
NESO project number
PRO-004654

Also at Moffat 400kV Substation

ProjectTechnologyMW
MinnygapOnshore wind25