Milligansbush Battery Storage

Milligansbush Battery Storage is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Milligansbush Battery Storage 132kV Substation (SPT). Status: Scoping. Gate 1.

Customer
Milligansbush Battery Storage Ltd
Connection site
Milligansbush Battery Storage 132kV Substation
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
25 Mar 2031
NESO project number
PRO-003430