Mill Hey_Capenhurst BESS

Mill Hey_Capenhurst BESS is a storage project of 199.6 MW in NESO's TEC Register of 23 Oct 2026, connecting at Capenhurst GSP (NGET). Status: Scoping.

Customer
FIRSTWAY SOLAR LTD
Connection site
Capenhurst GSP
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
199.6 MW
Agreement
Embedded
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-004669

Also at Capenhurst GSP

ProjectTechnologyMW
CapenhurstStorage, Solar400
Capenhurst 275KV SubstationStorage100
Capenhurst TertiaryStorage, Solar57
Capenhurst Tertiary ConnectionStorage57
CheshireGas90
Hill FarmStorage240
Native River (Capenhurst)Storage57

Source