Loch Luichart Extension II is a onshore wind project of 36 MW in NESO's TEC Register of 23 Oct 2026, connecting at Loch Luichart Extension II Substation (SHET). Status: Scoping. Gate 1.
- Customer
- BLUEBELL WIND FARM LIMITED
- Connection site
- Loch Luichart Extension II Substation
- Transmission owner
- SHET
- Technology
- Onshore wind
- Capacity (TEC)
- 36 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2024
- NESO project number
- PRO-000487