Llanwern 3

Llanwern 3 is a storage, solar project of 95 MW in NESO's TEC Register of 23 Oct 2026, connecting at South Wales East Connection Node A 275kV Substation (NGET). Status: Scoping.

Customer
FUTURE ENERGY LLANWERN LIMITED
Connection site
South Wales East Connection Node A 275kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
95 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-004317

Also at South Wales East Connection Node A 275kV Substation

ProjectTechnologyMW
SAE Usk 1Storage349
Whitson BESS NPStorage350