Lightsource Overton
Lightsource Overton is a storage, solar project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at North Humber Connection Node E 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- Lightsource Renewable UK Development Limited
- Connection site
- North Humber Connection Node E 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 240 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Oct 2035
- NESO project number
- PRO-003958
Also at North Humber Connection Node E 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Natpower Upsall Green Energy Park | Storage | 1,000 |
| OVERTON440MW BESS | Storage | 440 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.