Lightsource Mon Solar 2

Lightsource Mon Solar 2 is a storage, solar project of 120 MW in NESO's TEC Register of 23 Oct 2026, connecting at Wylfa South 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
LIGHTSOURCE SPV 204 LIMITED
Connection site
Wylfa South 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
120 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Nov 2037
NESO project number
PRO-002563

Also at Wylfa South 400kV Substation

ProjectTechnologyMW
Lightsourcebp Amlwch BESS and HydrogenDemand, Storage600
Mon Solar FarmStorage, Solar240–360