Lethans Wind Farm Extension

Lethans Wind Farm Extension is a onshore wind project of 85 MW in NESO's TEC Register of 23 Oct 2026, connecting at Lethans Collector 132kV Substation (SPT). Status: Consents Approved. Gate 2.

Customer
LETHANS EAST WIND FARM LIMITED
Connection site
Lethans Collector 132kV Substation
Transmission owner
SPT
Technology
Onshore wind
Capacity (TEC)
85 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
31 Oct 2029
NESO project number
PRO-003553