Grid GuardianOpen the evidence in the app

Lessnessock Energy Park

Lessnessock Energy Park is a storage project of 114 MW in NESO's TEC Register of 23 Oct 2026, connecting at LESSNESSOCK ENERGY PARK 132KV SUBSTATION (SPT). Status: Scoping. Gate 1.

Customer
RENEWCO POWER LIMITED
Connection site
LESSNESSOCK ENERGY PARK 132KV SUBSTATION
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
114 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-005033