Legacy 400

Legacy 400 is a storage, solar, onshore wind project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Legacy 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
ENSO GREEN HOLDINGS LIMITED
Connection site
Legacy 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar, Onshore wind
Capacity (TEC)
400 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-002193

Also at Legacy 400kV Substation

ProjectTechnologyMW
Legacy Green Energy CentreStorage400–1,200
Legacy Tertiary ConnectionStorage57
Plas Power Estate North TertiaryStorage, Solar57