Larks Green Farm BESS
Larks Green Farm BESS is a storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Iron Acton 132kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- VOLTALIA UK LTD
- Connection site
- Iron Acton 132kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 100 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2037
- NESO project number
- PRO-003849
Also at Iron Acton 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Iron Acton | Storage | 49.9–120 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.