Landulph

Landulph is a storage, solar project of 49.9–57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Landulph 400kV Substation (NGET). Status: Consents Approved, Scoping.

Customer
PIVOTED POWER LLP
Connection site
Landulph 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
49.9–57 MW
Agreement
Direct Connection
Status
Consents Approved, Scoping
MW effective from
18 May 2026, 31 Oct 2028
NESO project number
PRO-001131-1, PRO-001131-2

Also at Landulph 400kV Substation

ProjectTechnologyMW
Plymouth MainCHP (Combined Heat and Power)25.52
Plymouth RockCHP (Combined Heat and Power)15.08