Grid GuardianOpen the evidence in the app

Lacey's Farm BESS

Lacey's Farm BESS is a storage project of 924 MW in NESO's TEC Register of 23 Oct 2026, connecting at South Anglia Connection Node C 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Bluestone Energy Ltd
Connection site
South Anglia Connection Node C 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
924 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-004095

Also at South Anglia Connection Node C 400kV Substation

ProjectTechnologyMW
Cold NortonStorage, Solar, Onshore wind1,250
CorytonDemand, Solar1,000
NatPower Tilbury Green Energy ParkStorage1,000
Rat Hall Mod AppStorage, Solar200–700

Source