L48 BESS Glen App

L48 BESS Glen App is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at L48 BESS GLEN APP 275/132KV SUBSTATION (SPT). Status: Scoping. Gate 1.

Customer
S4 UK DEV LTD
Connection site
L48 BESS GLEN APP 275/132KV SUBSTATION
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-003058